Question 11 was stupid (1 Viewer)

Teh Duke

New Member
Joined
Nov 11, 2007
Messages
15
Gender
Male
HSC
2008
I put (A) but alot of people i talked to put (C). I think the evaluation doesn't count. The system is already finished after 7 weeks, and the evalution takes place after it's already been implemented.
Also, in the last bullet point about evaluation it already referred to it as "the network upgrade" which suggests that it's already finished...

What does everyone else think?
 

betonit169

My Username Sucks....
Joined
Oct 27, 2007
Messages
138
Location
Wagga Wagga
Gender
Female
HSC
2008
i think its C coz one week is done during others....

one week.... three weeks... two weeks... one week.... one week done while others are going... two weeks....

1 + 3 + 2 + 1 +2

=

9

=

C
 

hujikolp

Member
Joined
Oct 22, 2008
Messages
57
Gender
Undisclosed
HSC
2008
twas (c)
1+3+2(this is where 1 week overlaps--point 4)+1+2
 

Jake22

Member
Joined
Mar 24, 2008
Messages
130
Location
NSW
Gender
Male
HSC
2008
I would think evaluating is still part of the upgrade, because if determines that the original objectives arent met, then you start all over again.
 

betonit169

My Username Sucks....
Joined
Oct 27, 2007
Messages
138
Location
Wagga Wagga
Gender
Female
HSC
2008
Jake22 said:
I would think evaluating is still part of the upgrade, because if determines that the original objectives arent met, then you start all over again.

ooo smart


mehh i just counted the weeks without worrying about what they were doing
 

Terlob

Member
Joined
May 6, 2007
Messages
164
Location
Wagga Wagga
Gender
Male
HSC
2008
Nemanja said:
The correct answer is A.

REASON
  • Designing documentation - 1 Week
  • Research And Developement - 3 Weeks
  • Designing Solutions - 2 Weeks
  • Installation - 1 Week
  • WE ARE NOW AT 7 WEEKS (IT GETS TRICKY HERE)
  • After all instalations are complete (after 5 weeks) we have upgrade and evaluation for 2 weeks, therefore the upgrades and evaluations finish at the 7 week mark.
Hope this helped :)
The last 2 weeks still count, evaluation is part of the upgrade
 

Nemanja

Member
Joined
Jul 24, 2006
Messages
59
Gender
Male
HSC
2008
Terlob said:
The last 2 weeks still count, evaluation is part of the upgrade
Yes but they are commenced after all instalations are complete, all instalations are completed by the 5th week!!!

The answer is definitely A!
 

bao28

Member
Joined
Apr 29, 2007
Messages
67
Gender
Male
HSC
2008
Nemanja said:
The correct answer is A.

REASON
  • Designing documentation - 1 Week
  • Research And Developement - 3 Weeks
  • Designing Solutions - 2 Weeks
  • Installation - 1 Week
  • WE ARE NOW AT 7 WEEKS (IT GETS TRICKY HERE)
  • After all instalations are complete (after 5 weeks) we have upgrade and evaluation for 2 weeks, therefore the upgrades and evaluations finish at the 7 week mark.
Hope this helped :)
uh, in my major project, i included my evaluation of the whole project in my gantt chart, i did not get it wrong

and if it helps u might wanna revise on the 5 things

Testing, Evaluating & Maintaining is part of them
 

Terlob

Member
Joined
May 6, 2007
Messages
164
Location
Wagga Wagga
Gender
Male
HSC
2008
Nemanja said:
Yes but they are commenced after all instalations are complete, all instalations are completed by the 5th week!!!

The answer is definitely A!
The question asks for the minimum number of weeks for the network upgrade, not the installation.
 

Nemanja

Member
Joined
Jul 24, 2006
Messages
59
Gender
Male
HSC
2008
bao28 said:
uh, in my major project, i included my evaluation of the whole project in my gantt chart, i did not get it wrong

and if it helps u might wanna revise on the 5 things

Testing, Evaluating & Maintaining is part of them
Yes but they are commenced after all instalations are complete, all instalations are completed by the 5th week!!!

The answer is definitely A!
 

bao28

Member
Joined
Apr 29, 2007
Messages
67
Gender
Male
HSC
2008
Nemanja said:
Yes but they are commenced after all instalations are complete, all instalations are completed by the 5th week!!!

The answer is definitely A!
well your argument is wrong, however your answer might be correct

i'm reading the question

"What is the minimum number of weeks required for the network upgrade?"

shit fuck! crap FUCK
 

Teh Duke

New Member
Joined
Nov 11, 2007
Messages
15
Gender
Male
HSC
2008
"the network upgrade will undergo an evaluation". That means that the network upgrade is already finished when the evaluation starts.
 

Nemanja

Member
Joined
Jul 24, 2006
Messages
59
Gender
Male
HSC
2008
betonit169 said:
its still part of the installation :hammer:
Wrong again, the evaluation is not in the instalation, the instalation is in the IMPLEMENTING stage not the Testing, evaluating and maintaining stage.
 

bao28

Member
Joined
Apr 29, 2007
Messages
67
Gender
Male
HSC
2008
Teh Duke said:
"the network upgrade will undergo an evaluation". That means that the network upgrade is already finished when the evaluation starts.
but supposedly evaluation is part of the upgrade
 

betonit169

My Username Sucks....
Joined
Oct 27, 2007
Messages
138
Location
Wagga Wagga
Gender
Female
HSC
2008
looking into this question more and more makes my head hurt... and it confuses me
 

Terlob

Member
Joined
May 6, 2007
Messages
164
Location
Wagga Wagga
Gender
Male
HSC
2008
Nemanja said:
all instalations are completed by the 5th week!!!
Are you serious? No they aren't...

  1. Design and documentation - 1 week - 1 week so far
  2. Followed by research and dev - 3 weeks - 4 weeks so far
  3. Then design the solution - 2 weeks - 6 weeks so far
  4. Installation of cables - 1 week - 7 weeks so far
  5. Installation of software took place after research and dev - still 7 weeks
  6. Evaluation - 2 weeks - 9 weeks
Please note the last installation took place at 7 WEEKS

9 weeks = C
 
Last edited:

Users Who Are Viewing This Thread (Users: 0, Guests: 1)

Top