Originally posted by pocydto
I think it's supposed to be
x x x
.......x x x x
.......x x x x
.................x x
....................x
because the training of staff can happen at the same time as software installation and system testing. So I had 9 weeks Huy.
Originally posted by Leap
My gantt chart was in 9 weeks.
Damn. you guys are right.Originally posted by honky tonk
Task 5 had "This can occur at the same time as software installation and system testing", so I think the last two overlap, making it 9 weeks.
I skimmed it and thought it said the same as the above few.
"This can only start AFTER...."
Now I'm not so confident, thanks guys
...kidding!!